Tales from the Tower #2
Hey everyone!
We are making progress! Since our last update, the roof has been installed, as well as the doors and windows, we have power to the building, and our server room is nearly complete. Wallace Tower will be on-site Monday, Tuesday and Wednesday to begin preparations for the tower installation which, at this point, mainly consists of excavation for re-bar and concrete. Our fiber is still scheduled for installation mid May, but that is subject to changed.
Please share this with your friends and family and let them know that we are getting close to providing service.